Hi everyone, hope everyone is having a good weekend.
An update for production. Weāve received the 30 router mounts this past week as well as lead screws, drag chains, delrin ACME nuts, bearings, eccentric nuts, ACME locking nuts, and other stock. Power supplies, router mounts, spacers, control boards, and other parts are expected to arrive next week.
We ran into an issue with the delrin v-wheels from the shipment for this past week. The problem was that the v-wheels were manufactured out of spec, most notably for the outer diameter and inner angle of the v for each wheel. We have gone through every v-wheel that was shipped to us to see if we could find any that were to spec but unfortunately it appears that they are all out of spec.
Our manufacturer has agreed to help us and re-manufacture a new batch.
We had initially ordered 60 sets of v-wheels to temporarily tide us over until we received our complete batch of 500 sets (6000 v-wheels) to ship out the 20ish machines still waiting on our packing table. However, we want to make sure that the wheels are correctly made so that the machines work properly and as they should.
For the people who are currently waiting, we will need to get new v-wheels before we can ship.
We are currently doing two things to accommodate this delay.
-
Sourcing parts locally until we can have a larger batch of v-wheels arrive to cover our full waitlist.
-
Ordering a new batch of v-wheels and having them expedited to us as quickly as possible.
I have already placed an order for 250 sets of v-wheels (3000 v-wheels) which is expected to ship on Monday/Tuesday and arrive in about a week. This stock will cover the full backlog of machines.
Chris and I have also ordered some v-wheels from local sources that should arrive at the start of the week to cover for about 10-12 machines although we will have to see if they are of good quality as well.
Once I get tracking info for the new wheels I can provide some more updates on the status for the parts.